The Gantt Chart provides an alternative method for managing your construction schedule. You can switch from List View to Gantt View by simply clicking on the buttons:
The Gantt view offers a more visual approach for viewing and editing your schedule. It is particularly useful for making bulk changes to the schedule.
You have the flexibility to move the start date to any desired future date, and we automatically adjust the end date to maintain the same number of workdays.
Here are a few important points to consider:
- It is not possible to move the end date to a date prior to the start date. Therefore, you need to first adjust the start date, and the end date will automatically be adjusted accordingly.
- You cannot drag the start or end date of a schedule item to a non-working day, which is indicated by a darker grey background.
- To edit, add new items, mark them as complete, or delete them, you can click on the toggles shown in the picture. Hovering your mouse over these toggles will display the task name, start date, and end date.
Please note these guidelines while working with the Gantt view.
When you select "Edit," a new modal will open specifically for editing the schedule item.
Within the Gantt chart view, you will find buttons that allow you to extend or collapse phase items in the phase listing. Additionally, the Gantt chart offers zoom in/out options and a full-screen mode located on the right side.
The Gantt view provides the functionality to establish relationships between your schedule items.
To link two items together, you can hover over the end of one item, then click on the circle icon and drag it to the desired destination item. Double tab on the link line to undo it.
By extending a specific item, any linked contingent items will automatically be adjusted and pushed accordingly.
You can also filter the phases by date or add a new one.