BuilderPad's schedule utilizes a "Finish-To-Start" dependency by default, due to the nature of construction.
You can also add "Lag days" to create a buffer between tasks.
For example, if you need a two-day delay between the finish of one task and the start of another, you can establish a finish-to-start dependency and specify two days of lag time. You enter lag time as a positive value.
Adding dependencies from the list view:
Adding predecessors from the Gantt view: